Friday, August 26, 2011

Word Project - Waterproofing, slab

The underslab plumbing also ran into the continuing rock problem.  The plumber had to rent a jackhammer and chip a trench in order for the sewer line to have the correct slope/fall to the septic tank. 
6/1/2011

The waterproofing and foundation drain was completed on the first phase of foundation wall.  The drain was covered with filter fabric and covered with gravel.  We will lay more gravel before we backfill.

6/09/2011
The slab was poured and brushed smooth.  The slab will eventually be stained and sealed as the final finish.

6/20/11