Friday, November 11, 2011
Word - Update
Today at the site the backfilling has been in progress and the infilling between the retaining wall and the house. There is a lot to consider in this house while doing this work with water and power to the house, drainage lines for foundation water run-off and lines for future downspouts, catch basins installed, gravel over the foundation drains with filter fabric to insure water flows away from the house and the retaining wall.
Also the slabs were formed for the fireplaces on the main level and connector porch. The flue from the basement fireplace needed to come up and by-pass the firebox of the main floor fireplace so again, a lot of complicated figuring out the details to make sure the everything fits in the space allotted.